click for larger image


|
Horsey Substation – Seismic Upgrade
- Completion: February 2006
- Client: BC Hydro
- Prime Consultant: Sandwell Engineering
- Location: Victoria, BC
Seismic Upgrade to Electrical Substation Building. This project involved seismic upgrading of the existing substation building at Horsey Substation. Seismic footings, Dwidag anchors, concrete piers, concrete walls, and structural steel braces were tied to the existing structure. Adjoining duct banks and tower foundations were reinforced with concrete and tied to the substation building to prevent electrical conductors from collapsing during an earthquake.
|
|
|
|
|
|
|

click for larger image

|
Mt. Tolmie & Old Wesley Road Reservoirs ~ Seismic Upgrade
- Completion: April 1999
- Client: Municipality of Saanich
- Prime Consultant: Delcan Engineering
- Location: Victoria, BC
Seismic retrofit of existing reservoirs by hydroblasting of existing surfaces and attaching new reinforced concrete elements. Demolition of the existing surfaces commenced in January of 1999, wherein concrete surfaces were prepared by hydroblasting. Reinforcing steel was then attached to the existing structures by epoxy grouting dowels and concrete elements were formed and poured. The top surface of the existing upper Mt. Tolmie reservoir was completely covered with a new concrete slab.
|
|
|
|
|
|
|

click for larger image
|
Snowden Reservoir
- Completion: June 2004
- Client: District of Campbell River
- Prime Consultant: Dayton & Knight Engineers
- Location: Campbell River, BC
Construct a new concrete reservoir. Seismically upgrade an existing reservoir pump station and additional of a new generator building. Provide a new PRV chamber and SCADA systems. This project involved modifications to an operational water system, spread out over four different sites, throughout rural Campbell River, BC. Our work required careful scheduling and coordination to ensure that the system remained operational throughout construction. All required shut downs were carefully planned to ensure that there were little or no disruptions to the existing water service.
|
|
|
|
|
|
|

click for larger image


|
West Courtenay Reservoirs
- Completion: December 2001
- Client: Regional District of Comox-Strathcona
- Prime Consultant: Associated Engineering
- Location: Courtenay, BC
Construction of a 9.1 Million litre cast in place concrete reservoir and a 2.5 Million litre slip formed concrete (30 m high) reservoir. Work also included site works, control building, site piping and valves, and instrumentation.
|
|
|
|
|
|
|

click for larger image
|
Gorge Bridge Upgrade at Tillicum Road
- Completion: May 1999
- Client: District of Saanich
- Prime Consultant: Graeme & Murray Consultants
- Location: Victoria, BC
This project was conducted during the course of maintaining the bridge open to traffic at all time. The work involved coring & drilling through the bridge deck & abutments into the bedrock, installation of rock anchors, steel fabrications, removal of concrete deck surface by hydrodemolition and placement of a new concrete deck overlay complete with painted traffic lines & markings.
|
|
|
|
 |
|
|
|
|
|
|
|
|
|